On Friday the insulation company started their work. We chose a 2" layer of spray-in foam to seal all exterior walls. After this, cellulose will be blown in to fill the remainder of the wall studs and attic. There will be fiberglass batts installed in the garage, floor, and ceiling above the dining room (no attic). There are two more days of insulation to be completed before the sheetrock.



We tried to take Friday off, but just couldn't do it. We ended up with two huge bonfires to clean up some scrap lumber piles. We are trying to have as little trash as possible.



On Saturday and Sunday, we had to get back to work on the siding. We have temporarily lost the use of the big lift we were borrowing. Hopefully, we'll get it back soon or we'll be at a stand-still on the siding.



Ryan and Jenny installed all this siding this weekend.



Here's a nice Father's Day photo. We are really enjoying this project as a family. It's hard work, but it's so rewarding. We are so excited to be building our own home.

Wednesday, June 16, 2010

Barn Raisin'

Well, this weekend we had our own version of an Amish Barn Raisin'. Uncle Dave Heath and cousin Josh were so kind to offer their services with the electrical pre-wire. They brought Aunt Annie along and the ladies saw this as an opportunity for a family reunion, so we had quite the crowd. Cousin Mindy came with 3 week-old Avery and almost-8 year-old Kaya. Jenny's Mom and Dad came with their new baby, Ellie, seen lying on the front porch here.



Here, Josh drills holes on Day One.



Jenny's Dad, Gary, worked so hard to keep up with all the mess. We are very thankful for him this week as we're recovering from the weekend and the place is so nice, clean, and organized.



Here, Ryan watches as Uncle Dave installs a ceiling fan box.



We ended up with so many circuits, Uncle Dave had to go run for a sub-panel.

Friday, June 11, 2010

Tough as Nails

Yes, you are seeing this correctly. Jenny and Ryan are working on the siding. Enjoy it while you can, because once this lift goes any higher, Jenny will be signing off this job.



It was actually kind of fun!



The brick is now complete.



The garage floor is poured. No dogs this time. I do wish it could stay this nice.



And a Hidden Mickey of our own. It's a year 2000 Virginia quarter (wedding year), 2004 dime (for Ashton), and 2007 dime (for Quinn). Ryan's idea.

Monday, June 7, 2010

Let Ryan's Fun Begin!

Ryan and his friend Mike started on the exterior of the house this week since their job is still slow. This picture shows the soffit, which is actually being installed by the framers.



Here is Ryan on a very tall ladder measuring before installing a corner Miratec trim board. We chose Miratec trim and Nichiha fiber cement siding. Ryan and Mike are installing this. It is pre-primed and will need painted after installation.



I think the boys know more about the ipods than I do. You can see some of the siding work in the background here. Quinn is sitting on the front porch. The dog prints fade quite a bit if we rub them.



Here's a close-up of our siding (primed grey, unsure of final color). We're very happy with it so far.



Another view of the siding from the front of the house.

Wednesday, June 2, 2010

Who Let the Dogs Out?

They poured and broom-finished our front porch today.



Yes, this is what you think it is. Neighborhood dog. Not sure how to proceed with this one. This is the view from our front door.



The brick is complete on the front and sides of the house.



The brick on the back is coming along.



The garage floor is prepped for concrete tomorrow. Ryan will be there to put up dog barriers.

Friday, May 28, 2010

Puddlejumpers

We finally have windows! We chose the All-Ultrex Fiberglass windows by Marvin Integrity. We designed our own grille pattern. We wanted plain, but not too plain. We love this picture--check out that reflection! This is the last time you'll see them this clean.



Another window photo from the back side of the house. You can see the roofing progress here, too.



Our exterior doors also arrived this week. The brick guys are doing a nice job with all the details.



We had a huge thunderstorm this evening and the boys got into a bit of trouble while we were visiting with friends. They had so much fun!



I think we worked harder to get them into the car and bathed once home than we worked all day long!

Tuesday, May 25, 2010

Rough-ins and Brick



The brick is coming along.















This is the HVAC ductwork. We finally decided how to spend our HVAC budget. We will have a Trane Heatpump with CleanEffects filtration and a ventilator to introduce some fresh air.











Plumbing rough-ins are coming along.























Front exterior; windows come Friday. I'll believe it when I see it.

















Tubs are in place. This is the master bathroom. I have a feeling it will be a popular spot!